So per attached if you use NECA labor units about 1/2 the actual time is the installation and you can see the other parts that make up the rest.
So there is some NPL in there. On larger bids, say $500k + and if you use NECA units in a bid do you guys add separate non productive labor?
IMO essentially you'd be adding it twice unless you think there will be more than 5%.
So there is some NPL in there. On larger bids, say $500k + and if you use NECA units in a bid do you guys add separate non productive labor?
IMO essentially you'd be adding it twice unless you think there will be more than 5%.