I have contracted with a GC to perform the Electrical installation of a new Commecial Building. 80% of the way through the project the GC walks and I'm STUCK holding a $12,000 bill for installed material plus labor. (more to come) The Owner asks me to continue assuring me that all will be paid for and we do but! a week later he requests that we perfom two weeks work in five days and refuses to pay for additional manpower. When I refused because money to do the work is not there he asks me to leave (paying $0) and will find someone that can finish for the amount available.
My Question is : What course of action do we have short of attaching a Lien to the building and getting a lawyer involved ?
Had a feeling that this kind of **** would happen and lawyers would get rich but was to deep to stop all involvement, Just looking for a variety of actions different contractors have taken.
Thanks mjc
My Question is : What course of action do we have short of attaching a Lien to the building and getting a lawyer involved ?
Had a feeling that this kind of **** would happen and lawyers would get rich but was to deep to stop all involvement, Just looking for a variety of actions different contractors have taken.
Thanks mjc