Im in the process of putting together a bid for a job involving 40 feeders approximately 100 ft long to be incased in concrete. All to be done in RGS. Has anyone done something like this before any things to look out for . Be aware of? Code sections in particular to observe. Thanks I'm sure it's very easy to loose your shirt over a small oversight.

Sent from my SM-G950U using Tapatalk
 
Spacing of conduits is critical it's likely that advanced engineering calculations are used to size the feeders so the conditions are very precise