mstrlucky74
Senior Member
- Location
- NJ
Engineer is asking for the following.
So regarding phasing notes 1 & 3( see attached).
I also only attached a portion of the EM riser but enoughthat you can see the new switch that feeds the 300kva( that that they areasking to be used a source of temp power) and from there the xfrmr feeds a busdetail and switches which feed other equipment.
So according to phasing note # 1 they want this EM schemeinstalled and up and running. Then in phasing note #3 they want us to temp out(5) 600A distribution panels( notnecessarily at once).
My question is how could the 300kva xfrmr be used as a temppower source if it’s already being used for it’s intended uses as shown on theone line and spelled out in phasing note #1? Is this possible even if youshutdown power to make temp connections could the xfrmr handle all that?
I’m thinking once everything is up and runningper phasing note # 1 then you would have to disconnect the 120/208v side (3)sets and safe it off then run your temp from the xfrmr to the distributionpanels then when temp is no longer needed connect back the (3) sets.
Thanks a lot for any input/advice.
So regarding phasing notes 1 & 3( see attached).
I also only attached a portion of the EM riser but enoughthat you can see the new switch that feeds the 300kva( that that they areasking to be used a source of temp power) and from there the xfrmr feeds a busdetail and switches which feed other equipment.
So according to phasing note # 1 they want this EM schemeinstalled and up and running. Then in phasing note #3 they want us to temp out(5) 600A distribution panels( notnecessarily at once).
My question is how could the 300kva xfrmr be used as a temppower source if it’s already being used for it’s intended uses as shown on theone line and spelled out in phasing note #1? Is this possible even if youshutdown power to make temp connections could the xfrmr handle all that?
I’m thinking once everything is up and runningper phasing note # 1 then you would have to disconnect the 120/208v side (3)sets and safe it off then run your temp from the xfrmr to the distributionpanels then when temp is no longer needed connect back the (3) sets.
Thanks a lot for any input/advice.