We have a project with a tight vertical fit. Our primary feeds running to a transformer will have to run through the bottom of the enclosure of the secondary OCPD of said transformer. NEC 200.6(D), 210.4(D), and 300.4(C)(1) seem to indicate this is ok. Anyone else run into this?