SomeRandomPerson
Member
- Location
- Massachusetts
- Occupation
- Electrician
With the new meter main breakers outside of the home, it’s caused some confusion for me as an apprentice. I have one journeyman who insists that if you are doing a panel/ meter swap with SEU cable, your ground rods are terminated in the meter main as a #8 conductor while your water main is the EGC with a #6 that’s brought to the panel and terminated.
Another guy says the water meter ECG is brought to the meter main and the ground rods conductor is also brought back there. Any help? Who’s right?
Sent from my iPhone using Tapatalk
Another guy says the water meter ECG is brought to the meter main and the ground rods conductor is also brought back there. Any help? Who’s right?
Sent from my iPhone using Tapatalk