Toros
Senior Member
- Location
- Tujunga, CA
Hi
I am wondering that,
Why utility the local company (LADWP) cut the power at their power pole on this tenant????
(supplying an existing warehouse doing welding with an existing 3 phase 1200A service, single meter)
LADWP says "over loading"
How do they knew it was over load ????
note that, supplying conductors have 230A apoxim. sized base on previous tenant's demand load.
Thank you
I am wondering that,
Why utility the local company (LADWP) cut the power at their power pole on this tenant????
(supplying an existing warehouse doing welding with an existing 3 phase 1200A service, single meter)
LADWP says "over loading"
How do they knew it was over load ????
note that, supplying conductors have 230A apoxim. sized base on previous tenant's demand load.
Thank you