Utility Scale PV Engineering

Status
Not open for further replies.

BandGap1.1eV

Member
Location
East Coast
Good afternoon All -

Looking to poll the audience for estimated PV engineering costs associated with CD's for a 20 MWdc ground mount. Excluding the cost of the MV engineer to design the substation.

Estimated order of magnitude? $250k?
 
Discussion of the pricing of services among service providers generally violates anti-trust laws. At least that's what they say before every SEIA meeting I have been in.
 
Status
Not open for further replies.
Top