Greenautomator
Member
- Location
- United States
This is for an EV site, a utility transformer is feeding a 2000 amp discount.
Main bond jumper installed here tied to 2 ground rods.
The 2000 amp disconnect feeds 8 450A disconnects.
Each feed to a 480V 400A fused disconnect.
Each 400A fused disconnect feeds a 167KVA transformer 480V single phase primary to 240/120V single phase secondary.
Each Transformer feeds 2 120/240 branch 400A branch panels, each having 4 2 pole 100A breakers for EV chargers.
EV's together are limited to 320A
Question is if each of these transformers need its own ground rod?
Main bond jumper installed here tied to 2 ground rods.
The 2000 amp disconnect feeds 8 450A disconnects.
Each feed to a 480V 400A fused disconnect.
Each 400A fused disconnect feeds a 167KVA transformer 480V single phase primary to 240/120V single phase secondary.
Each Transformer feeds 2 120/240 branch 400A branch panels, each having 4 2 pole 100A breakers for EV chargers.
EV's together are limited to 320A
Question is if each of these transformers need its own ground rod?