Cost Cutting
Cost Cutting
Value engineering / more economical / cost effective / call it what you will a good topic some of these may have been mentioned previously off the top of my head:
One thing I always look at is in industrial applications is the conduit type Rigid Steel vs EMT vs Rigid AL, the rigid AL is lighter and will install easier / faster than Rigid Steel if EMT is off the table
If the project calls for cable tray and IAC cable you can look at using tri-plexed tray rated cables usually with the increased ampacity ratings you may be able to drop a set of conductors if it is a parallel run.
AL vs CU for conductors, xfmr. windings, panel busing
Sw.Gear / Sw.Board / Panel board type constructions
using 10Kaic panels for RP's fed from xfmr.'s I have seen many times RP's fed from 75, 45, 30, or 15kVA xfmr.'s requesting 22kAIC where 10kAIC is adequate
Look at the wiring methods is the project specifications indicated all conduit, MC can be a good VE
using feeder MC type cable in some applications
Rings and strings for LV cable & using plaster rings in lieu of conduit and oversized backboxes for LV locations
using modular wiring [re-lock] for high bay fixture applications
not really a VE but I have noticed a lot of contractors now using "pre-fab" techniques, for example in offices or areas where there are a lot of typical assemblies they have these assemblies pre-made in their shop [receptacle, backbox, whip, protector plate] so once they get on site they are installing them not having to put them together on site. Just one example. I know one contractor that will even pre-plan pipe routes and have the conduit bent and ready to install when it arrives on site.