Joe A
Member
- Location
- Holland,Pa
When installing a 3/4 or 1” EMT in the wall from a data box at 18”
and stub 90 above the ceiling it’s at least a full stick of pipe. How many supports are required ?
i typically use 2 one from the box 12”- 3’ and then one before the stub 90.
This was a topic of conversation at work and my Forman said only one support 3’ from the box.
I disagree the code states min 3’ from termination point. I say that stub 90 is also a termination and or end of pipe. Just looking for a few other inputs.
thanks
and stub 90 above the ceiling it’s at least a full stick of pipe. How many supports are required ?
i typically use 2 one from the box 12”- 3’ and then one before the stub 90.
This was a topic of conversation at work and my Forman said only one support 3’ from the box.
I disagree the code states min 3’ from termination point. I say that stub 90 is also a termination and or end of pipe. Just looking for a few other inputs.
thanks