olly
Senior Member
- Location
- Berthoud, Colorado
- Occupation
- Master Electrician
Does anyone see a problem with this Install, I have already done the VD calculation it requires 500kcmil for the distance so just asking about the install.
Come out of the meter that's on a pole with 4/0 AL, to a splice box splicing into two parallel runs of 250 kcmil AL, running a distance of 320' to another splice box to step the wire back down to 4/0 AL then entering the house to hit the breaker panel.
Calculation was based off south wires online calculater
Thanks
Come out of the meter that's on a pole with 4/0 AL, to a splice box splicing into two parallel runs of 250 kcmil AL, running a distance of 320' to another splice box to step the wire back down to 4/0 AL then entering the house to hit the breaker panel.
Calculation was based off south wires online calculater
Thanks