• We will be performing upgrades on the forums and server over the weekend. The forums may be unavailable multiple times for up to an hour each. Thank you for your patience and understanding as we work to make the forums even better.

Voltage Drop

Merry Christmas

Alwayslearningelec

Senior Member
Location
NJ
Occupation
Estimator
Not sure if I'm calcuting this correct for primary(277/480v) side.

Have RGS conduit and copper XHHW wire going from a 100AF/70AT breaker in switchboard 850' to 70A enclosed breaker and then primary side xfrmr.

They are saying to run 3#350 & #3/0. Seems oversized. I come up with 4/0 to keep under 3% VD.

BTW when plugging in valued to VD calcutor how would I know whether to use 277 or 480v? Thanks


1730336525442.png
 

Julius Right

Senior Member
Occupation
Electrical Engineer Power Station Physical Design Retired
If I use NEC Table 9 [Effective Z for steel conduit] I get for 1/0 2.79% drop.
 

PD1972

Member
Location
New York (2017 NEC)
Occupation
engineer
It looks like the transformer is going to be 45kVA, so I would use 54A at 480V for the calculation.

Based on the 350kcmil (at copper) the drop at full load of the transformer is ~1%VD. Is that what the designer is trying to do by leaving 4%VD for everything fed from that panelboard?
 

augie47

Moderator
Staff member
Location
Tennessee
Occupation
State Electrical Inspector (Retired)
It looks like the transformer is going to be 45kVA, so I would use 54A at 480V for the calculation.

Based on the 350kcmil (at copper) the drop at full load of the transformer is ~1%VD. Is that what the designer is trying to do by leaving 4%VD for everything fed from that panelboard?
Forgive my "stupid" but I don't understand that.....
the transformer appears to be the only load on the 480 v feeder and if he keeps that to 3% at full current that should not affect the panleboard load should it ??
 

PD1972

Member
Location
New York (2017 NEC)
Occupation
engineer
Forgive my "stupid" but I don't understand that.....
the transformer appears to be the only load on the 480 v feeder and if he keeps that to 3% at full current that should not affect the panleboard load should it ??
Total allowable combined VD between feeder and branch circuit per adopted state energy codes I am familiar with has been 5%.

OP mentions the feeder is coming from a switchboard, which I am assuming to be the service. You can definitely keep the feeder VD to 3% between switchboard and transformer as it wouldn't technically affect panelboard loads; however, branch circuit conductor sizes of circuits fed from the panelboard may be larger to achieve a 2% branch circuit VD.

A 1% feeder VD between switchboard and panelboard would allow for branch circuit conductor sizes to be sized to 4% max VD. I do not know if the increased cost in a larger feeder would offset the cost of larger branch circuit conductors, but that is (in my opinion) what would drive the decision.
 
Top