C coryp Member Aug 28, 2008 #1 Can someone point me in the right direction to where in the code (I know its in there somewhere) you are required to upsize the ground if you upsize the phase and neutral. Thanks.
Can someone point me in the right direction to where in the code (I know its in there somewhere) you are required to upsize the ground if you upsize the phase and neutral. Thanks.
acrwc10 Master Code Professional Location CA Occupation Building inspector Aug 28, 2008 #2 250.122(b)