For code for water pipe bonding on a well system; I usually install the bonding conductor to the nearest cold water pipe, then just jump out the water heater, and if gas, jump to gas pipe. on city water, It depends on if incomming water is poly or copper. I'll still have to jump out water meter and heater, but still not sure if the bonding conductor still must be run total length to water entrance on both water entrance materials (poly and copper). Also if water entrance piping is copper, Is a ground rod(s) still required? Any help;