A two-inch metal offset nipple is installed between the meter housing and the panel of a 120/240-volt, 200-ampere service. When is the nipple REQUIRED to be bonded?
1. Always.
2. When locknuts are wrenched tight.
3. When concentric and eccentric are not present.
4. When an equipment grounding conductor is installed from the meter to the panel.
Thanks for your help
Julian
1. Always.
2. When locknuts are wrenched tight.
3. When concentric and eccentric are not present.
4. When an equipment grounding conductor is installed from the meter to the panel.