Relocate the service and make the existing panel into a sub-panel.

If you plan it right, the power should be off and back on in one day.
 
Thanks, that thought had crossed my mind on jobs like this in the past. I’m still kind of hoping for a less involved solution.
If you don't want a temp pole then they'll have to built the addition around the existing service. Once the new area is framed move the service.
 