gar
Senior Member
- Location
- Ann Arbor, Michigan
- Occupation
- EE
130425-2150 EDT
This evening our local SME (Society of manufacturing Engineers) chapter visited the Dowding Industries plant in Eaton Rapids, Michigan.
Here they have what is probably the longest bridge mill in the world. The base is 106' long and they can mill a part up to 96 ft long. To date the longest part has been 65'. The primary purpose of the machine is to machine the form for making wind turbine blades. The accuracy is on the order of 0.001" over the 96'. It is a 5 axis MAG machine.
Another special CNC machine they have has 3 heads, each with a 100 HP spindle motor, and a central rotary table. This machine is use to machine the raw casting for the turbine rotor hub. The raw casting is about 45,000 #, and after machining about 40,000 #. A single hub can be machined in about 6 hours where previously a single spindle machine required about 26 hours. The machine cost $14,000,000.
Another machine, not at this location, is a CNC to lay up the carbon fiber sheets on the blade form for turbine blades.
These machines are helping to reduce the cost of a wind turbine. and therefore the cost to generate electricity.
Currently the hub castings come from China or Finland, and besides transportation costs there is about $14,000 spent just to package the casting for shipment. Plans are in the works to build a casting plant just across the street from the machining plant. This will be the first new casting plant in the US in about 40 years. Big cost savings here.
There are a considerable number of wind farms being installed in Michigan. So some of these parts are directly used in Michigan.
Since the thruput of the machines is much greater than demand the machines get used to make other large objects. There is continuous demand for large parts used in fracking. This is continuous because the parts only last about 300 hours.
.
This evening our local SME (Society of manufacturing Engineers) chapter visited the Dowding Industries plant in Eaton Rapids, Michigan.
Here they have what is probably the longest bridge mill in the world. The base is 106' long and they can mill a part up to 96 ft long. To date the longest part has been 65'. The primary purpose of the machine is to machine the form for making wind turbine blades. The accuracy is on the order of 0.001" over the 96'. It is a 5 axis MAG machine.
Another special CNC machine they have has 3 heads, each with a 100 HP spindle motor, and a central rotary table. This machine is use to machine the raw casting for the turbine rotor hub. The raw casting is about 45,000 #, and after machining about 40,000 #. A single hub can be machined in about 6 hours where previously a single spindle machine required about 26 hours. The machine cost $14,000,000.
Another machine, not at this location, is a CNC to lay up the carbon fiber sheets on the blade form for turbine blades.
These machines are helping to reduce the cost of a wind turbine. and therefore the cost to generate electricity.
Currently the hub castings come from China or Finland, and besides transportation costs there is about $14,000 spent just to package the casting for shipment. Plans are in the works to build a casting plant just across the street from the machining plant. This will be the first new casting plant in the US in about 40 years. Big cost savings here.
There are a considerable number of wind farms being installed in Michigan. So some of these parts are directly used in Michigan.
Since the thruput of the machines is much greater than demand the machines get used to make other large objects. There is continuous demand for large parts used in fracking. This is continuous because the parts only last about 300 hours.
.