Someone please set me straight on this.
My understanding is that for regular residential service, you would need 3x 4/0 aluminum wire or 3/0 copper wire from the meter to the load center.
Is this right?
If so, when we took off the meter, the wire coming in from the utility was just #2 copper. Asked the guys from the POCO and they said no problem.
What is the point of running 4/0 wire from the meter if the wire coming into it is just #2? Please set me straight.
In case it matters, the service here is fully underground (no poles, aka BUD) and is supplied by PSE&G in south jersey.
My understanding is that for regular residential service, you would need 3x 4/0 aluminum wire or 3/0 copper wire from the meter to the load center.
Is this right?
If so, when we took off the meter, the wire coming in from the utility was just #2 copper. Asked the guys from the POCO and they said no problem.
What is the point of running 4/0 wire from the meter if the wire coming into it is just #2? Please set me straight.
In case it matters, the service here is fully underground (no poles, aka BUD) and is supplied by PSE&G in south jersey.