If I use a wireway as a junction box, do I have to derate?
The scenario is a 6’ length of 12”x12” wireway, I am mounting on wall, coming into the far backside with 3- 2 1/2” conduits, than nippleing 3’ down on opposite side of wireway with the 3 conduits into panel
Sent from my iPhone using Tapatalk
The scenario is a 6’ length of 12”x12” wireway, I am mounting on wall, coming into the far backside with 3- 2 1/2” conduits, than nippleing 3’ down on opposite side of wireway with the 3 conduits into panel
![053821f8d1b67b857c74f73da40de229.jpg](http://uploads.tapatalk-cdn.com/20181127/053821f8d1b67b857c74f73da40de229.jpg)
Sent from my iPhone using Tapatalk