at the present time this 15 story apartment
building is empty and gutted. we shall be bring
in two meter sections, a main and 90 meters, one for either side. we do have 2 full length shafts. i want to go up with emt thru to each apartment panel (100amps) and then the new brach circuits exposed in wiremold, where required. my question is, is there anywhere in the code,or do i just call the town inspector and see what he allows, to find out what i can or cannot use.
building is empty and gutted. we shall be bring
in two meter sections, a main and 90 meters, one for either side. we do have 2 full length shafts. i want to go up with emt thru to each apartment panel (100amps) and then the new brach circuits exposed in wiremold, where required. my question is, is there anywhere in the code,or do i just call the town inspector and see what he allows, to find out what i can or cannot use.