We are bidding a 4 story hotel in San Luis Obispo. The structure is wood construction. We just finished a 3 story hotel in Atascadero, CA where we were allowed to wire just the rooms with NM cable (Romex). All other areas were either wired with MC cable (concealed) or EMT (where exposed). Both of these projects have been designed by the same Achitect and Electrical Engineer.
My Question: Can we apply the same wiring methods, as used on the 3-story hotel, on a 4 story hotel?