We have a new facility that has a 1200AMP/480VAC/3PH service.
The new switchgear is located inside the building along a wall. We need access to "Pull A Pump" through an opening in the floor. This opening is in the designated work space of the Switch Gear with removable floor grating. When the pump is being pulled, the floor grating is removed and gaurd rails are installed in sleeves in the floor.
Question:
Since the removable gaurd rails are only installed when the pump is being pulled, is this okay?
The new switchgear is located inside the building along a wall. We need access to "Pull A Pump" through an opening in the floor. This opening is in the designated work space of the Switch Gear with removable floor grating. When the pump is being pulled, the floor grating is removed and gaurd rails are installed in sleeves in the floor.