hotblueelectric
Member
- Location
- Dallas Texas
I am remodeling a residential home turned into commercial bld for office space. I am upgrading the service from 150 to 200 amp and moving it from one area in what used to be the garage over about 6-8 feet which will now be a utility room. Mounted the panel and ran my conduit from meterbase to the new location. Now the customer has informed me that a floor sink will be installed next to the water heater and this will be right next to the 200 amp panel about 10" away. Looking at Table 110.2 (A) (1) I need 3' to each side of the panel I have 3 feet over to left between the panel and water heater and less to the right because of a wall there. Can I mount the panel there with a floor sink next to the panel. I cant find anything in the code otherwise.
Thank you
HL Electrical Contractor.
Thank you
HL Electrical Contractor.