Does NEC 2014 section 110.26, 3 feet working space apply to Fire Alarm Control Panel 120V single phase or not?
I don't do Fire alarm panels but, like Wlaricci said, If you can't de-energize it to work on it then yes you would have to have 110.26 clearance.It depends on if it is likely to require examination, adjustment, servicing, or maintenance while energized.
Sent from my Pixel 3a using Tapatalk