Good morning all
I have a Primary transformer DELTA/DELTA 70KV TO 12KV. within the last five years the facility has added solar to the site with BESS. The old system has a MV distribution of wye delta transformer in the plant and the new system has wye grounded PTs for measuring and the SEL ground fault protection. When we deenergize the system for maintenance or inspection we cannot get the plnat back on line with out deracking the PTs and force the system on
How does the PTs wye grounded and the DELTA system interact? Why does is not consistently interact? How would someone approach fixing this system to ensure its safety and operations
I have a Primary transformer DELTA/DELTA 70KV TO 12KV. within the last five years the facility has added solar to the site with BESS. The old system has a MV distribution of wye delta transformer in the plant and the new system has wye grounded PTs for measuring and the SEL ground fault protection. When we deenergize the system for maintenance or inspection we cannot get the plnat back on line with out deracking the PTs and force the system on
How does the PTs wye grounded and the DELTA system interact? Why does is not consistently interact? How would someone approach fixing this system to ensure its safety and operations