A client is proposing to retrofit a NEMA 4 pump control enclosure for use in a Class I Div 2 location by field installing a listed purge / pressurization unit from Pentair (Hoffman).
I've normally seen the purged units factory assembled in the panel shop as part of a listed industrial control panels.
Are there any issues with performing field retrofit, assuming the sizing/flowrates are properly calculated in accordance with mfr instructions? Any things to watch out for? As this is Z purge, and based on my read of NFPA 496 I think they are only required to alarm on loss of pressure, and don't need to trip the power supply to the enclosure. Is this correct?
I've normally seen the purged units factory assembled in the panel shop as part of a listed industrial control panels.
Are there any issues with performing field retrofit, assuming the sizing/flowrates are properly calculated in accordance with mfr instructions? Any things to watch out for? As this is Z purge, and based on my read of NFPA 496 I think they are only required to alarm on loss of pressure, and don't need to trip the power supply to the enclosure. Is this correct?