For an obsolete sub-transmission system chunk without active breaker failure protection, would anyone see an issue reducing Zone 2 delays down to 8 cycles instead of the typical 20-25 cycle delay? In so far the reduced zone 2 delay appears to be advantageous for generation but I am sure I am missing something.