Okay, before we begin, let it be clear that I do not have all the information here. So my following question is not mine or how this even happened.
My dad is remodeling his shop and the time is arriving to wire the 3 phase air compressors back up. The electrician we hired said that he cannot go from the service entrance box directly to the motor controllers, he has to go through the circuit breaker box before he can go anywhere else. My father disagree's and cannot see why the NEC would require such a thing.
So I suppose I am looking for the part of the code that says "3 phase conductor's must be wired through the central box."
My dad is remodeling his shop and the time is arriving to wire the 3 phase air compressors back up. The electrician we hired said that he cannot go from the service entrance box directly to the motor controllers, he has to go through the circuit breaker box before he can go anywhere else. My father disagree's and cannot see why the NEC would require such a thing.
So I suppose I am looking for the part of the code that says "3 phase conductor's must be wired through the central box."