I have a question I hope someone can answer, I am currently in Iraq working as a electrician and I have run across this situation a couple of times. There will be 2 generators feeding a 3-pole transfer switch with no EGC ran with the cables, just 3 hots and a neutral. The generators are both bonded and the transfer switch frame is then bonded to the neutral at the switch. There is no other metal parts connecting the gens and transfer switch which would create a parallel path. My question is this okay per the NEC.
Thanks,