I have to feed some equipment in a comm kitchen .
the equipment is all in the middle of the kitchen , I was planning on
doing Cord drops with sj cord and putting twist locks on each end with the strain relief on the end that enters the box.
i was planing on attaching 1900 box to a bar braket and cut the box flush with the suspended
ceiling tile.
then using the 1/2 hole in a blank cover plate and have the sj cord group straight down from the cover plate .
i wanted to do this to keep the sj cord out of pre hung ceiling .
is this install being to picky or would most guys just cut corner of ceiling tile and have sj enter into box above the ceiling ?
the equipment is all in the middle of the kitchen , I was planning on
doing Cord drops with sj cord and putting twist locks on each end with the strain relief on the end that enters the box.
i was planing on attaching 1900 box to a bar braket and cut the box flush with the suspended
ceiling tile.
then using the 1/2 hole in a blank cover plate and have the sj cord group straight down from the cover plate .
i wanted to do this to keep the sj cord out of pre hung ceiling .
is this install being to picky or would most guys just cut corner of ceiling tile and have sj enter into box above the ceiling ?