How do you answer the "how much do you charge" and "how long will it take" question?

Status
Not open for further replies.

kwired

Electron manager
Location
NE Nebraska
Let me see if I understand:
You gave them a bid. You know the hours. You know the crew.

And you can't give them an estimated completion date? And you think the customer is leaning on you when they ask for a completion date?

ice
If other trades are involved, completion date may not be very predictable. I can have it done by such and such date IF, the framers meet a particular schedule, IF walls are finished at a predetermined time, IF the HVAC guys get their equipment in place by a specific time.....
 

iceworm

Curmudgeon still using printed IEEE Color Books
Location
North of the 65 parallel
Occupation
EE (Field - as little design as possible)
If other trades are involved, completion date may not be very predictable. I can have it done by such and such date IF, the framers meet a particular schedule, IF walls are finished at a predetermined time, IF the HVAC guys get their equipment in place by a specific time.....
Okay, that's true.

ice
 
If other trades are involved, completion date may not be very predictable. I can have it done by such and such date IF, the framers meet a particular schedule, IF walls are finished at a predetermined time, IF the HVAC guys get their equipment in place by a specific time.....

+1...just got burned on a job because framers weren't done with wall, floors weren't done, etc.....ended up making 4 trips just for rough now going back tomorrow to trim out...probably gonna have $600 in drive time by the end of job. Didn't figure that in!!!


Sent from my iPad using Tapatalk
 
Status
Not open for further replies.
Top