If other trades are involved, completion date may not be very predictable. I can have it done by such and such date IF, the framers meet a particular schedule, IF walls are finished at a predetermined time, IF the HVAC guys get their equipment in place by a specific time.....Let me see if I understand:
You gave them a bid. You know the hours. You know the crew.
And you can't give them an estimated completion date? And you think the customer is leaning on you when they ask for a completion date?