My question is about the Service Entrance Conductors into the building. Were in the NEC does it mandate that the Service Entrance conduit is to be encased in 2" of concrete. I have abided by Article 230.43.
I would think 230.6 is acknowledging that if the conduits are under 2" of concrete it would be an outside conductor, not that the conduit has to be under the 2" of concrete.