al hildenbrand
Senior Member
- Location
- Minnesota
- Occupation
- Electrical Contractor, Electrical Consultant, Electrical Engineer
A dwelling built in 1952, had an addition and relocation of the service entrance and service disconnect around 1975. The original panel had its overcurrent devices and bus assembly removed, except for the neutral bar.
The original branch circuits were extended from the old panel to the new service center.
My question: Was there a way, by Code, from around 1975, to use that old neutral bar to splice all the neutrals, downstream of the old panel, together into one massively parallel set of neutrals between the old panel and the new service center?
The original branch circuits were extended from the old panel to the new service center.
My question: Was there a way, by Code, from around 1975, to use that old neutral bar to splice all the neutrals, downstream of the old panel, together into one massively parallel set of neutrals between the old panel and the new service center?