- Location
- Chapel Hill, NC
- Occupation
- Retired Electrical Contractor
Imagine a service lateral to a building that goes into a wireway at the front of a building and feeds 4 meter/mains. The service conductors are then spliced in the wireway and continue in conduit, on the building, around the corner to the right side of the building where another set of 4 meter/mains are installed. This continues to the other 2 sides of the building.
1. Is this one service? As I understand it the answer is YES
2. Is the install legal if it is one service and there are 16 service disconnects that are not even grouped?
3. If it is compliant then would ground rods be needed at each side of the building? I know it may be a good idea but I am looking for code.
If you know code sections that would be useful ---Thanks
1. Is this one service? As I understand it the answer is YES
2. Is the install legal if it is one service and there are 16 service disconnects that are not even grouped?
3. If it is compliant then would ground rods be needed at each side of the building? I know it may be a good idea but I am looking for code.
If you know code sections that would be useful ---Thanks