PV conductors run in attic

Status
Not open for further replies.

jasonbone

Member
Location
North Carolina
[FONT=&quot] [/FONT]
[FONT=&quot]Under 2011 code 690.31(E)(1) stated that wiring methods beneath a roof shall not be installed within 10in of roof deck…[/FONT]
[FONT=&quot] [/FONT]
[FONT=&quot]I can’t find any such code in the 2017 version. Has the implementation of 690.12 and rapid shut down systems deemed the 10in rule no longer a concern?[/FONT]

[FONT=&quot] [/FONT]
[FONT=&quot]Any clarification appreciated.[/FONT]

[FONT=&quot]
[/FONT]
 

PaulMmn

Senior Member
Location
Union, KY, USA
Occupation
EIT - Engineer in Training, Lafayette College
I'm aware of the rule that says you have to make sure your wiring under a roof deck needs to be out-of-the-way of any roofing nails that might be installed later... but 10" seems excessive.
 

jasonbone

Member
Location
North Carolina
I'm aware of the rule that says you have to make sure your wiring under a roof deck needs to be out-of-the-way of any roofing nails that might be installed later... but 10" seems excessive.
It was to allow firefighters to safely axe through a roof without fear or cutting into a 600VDC wire from roof mounted PV. Hence my wondering if the introduction of rapid shut down did away with this code.
 