five.five-six
Senior Member
- Location
- california
Starting my first install presently, I started slow. Red some books, took some classes, opened an account with CED/greentech, and started an account with an engendering firm that draws up plans that seem to sail through plancheck.
My first job is on my own house... didn’t want to put any customer through any trial and error.
System will be 26 Hyundai mono crystalline 290W modules, solar edge optimizers and a solar edge SE6000H
Racking is Iron ridge XR10 and I’m doing supports on 48”
* Here is my first question, how far apart do I need to space the rales apart. I didn’t find any specification. It seems like there is a lot of leeway so long as the modules land on the rails on the outer 12” or so.
* 2nd question, and I think I know this... PV wire on the roof to the JB or combiner box and then #10THHN back to the inverter in a metal raceway marked with PV stickers and nothing else in it except the EGC? Is that right?
My first job is on my own house... didn’t want to put any customer through any trial and error.
System will be 26 Hyundai mono crystalline 290W modules, solar edge optimizers and a solar edge SE6000H
Racking is Iron ridge XR10 and I’m doing supports on 48”
* Here is my first question, how far apart do I need to space the rales apart. I didn’t find any specification. It seems like there is a lot of leeway so long as the modules land on the rails on the outer 12” or so.
* 2nd question, and I think I know this... PV wire on the roof to the JB or combiner box and then #10THHN back to the inverter in a metal raceway marked with PV stickers and nothing else in it except the EGC? Is that right?
Last edited: