brian john
Senior Member
- Location
- Kilmarnock, Va
- Occupation
- Retired after 52 years in the trade.


The complete risers, 2 of them in a 12 story building plus horizontal runs, All busway connections were loose.
Should have called this thread Friday Pic's
![]()
What's worse than the wire handle tie is that the bolt-on CB opposite the blue conductor is not bolted to the bus.
![]()
Are those smaller wire double lugged? Or maybe they are terminated with ring terminals under the lug....
I just have to say that when techs double lug these tiny (comparatively) wires onto the power lugs is drives my nuts!
Bad crimp on a Mac Adapt type connector.
![]()
![]()
I'm curious to know how it's the crimp and not just a unbalanced load on that phase?
We did not get the repair, our IR tech does current readings and FOP readings on all IR discrepancies.