That has been my experience.
For example I would say 90% of our prints indicate an EMT job but we use MC
For those under the I-Codes: (this includes all trades)
106.4 Amended construction documents. Work shall be
installed in accordance with the approved construction documents,
and any changes made during construction that are not
in compliance with the approved construction documents shall
be resubmitted for approval as an amended set of construction
documents.
For those in PA: (again, includes all trades)
(l) Work shall be installed in accordance with the approved construction documents. The permit holder shall submit a revised set of construction documents for approval for changes made during construction that are not in accordance with the approved construction documents.
(m) A permit is not valid until the required fees are collected under ?? 401.2 and 401.2a (relating to Department fees; and municipal and third-party agency fees).