Greetings All,
I just got a question about a three gang box with a mud ring where the wall covering (double layer sheetrock) is greater than 15/16". Apparently they do not make a mud ring deeper than 13/16 for greater than two gang rings. The CBC requires no more than a 1/8" gap from device ring to FOF. I am unsure if this applies in the case of low voltage.
What are the solutions for this type of situation?
Thanks,
MacG
I just got a question about a three gang box with a mud ring where the wall covering (double layer sheetrock) is greater than 15/16". Apparently they do not make a mud ring deeper than 13/16 for greater than two gang rings. The CBC requires no more than a 1/8" gap from device ring to FOF. I am unsure if this applies in the case of low voltage.
What are the solutions for this type of situation?
Thanks,
MacG