guitarchris
Senior Member
- Location
- Central North Carolina
I've been asked by a local town to install provisions for connecting a 65K portable Generator to 4 or 5 sewer lift pump stations. They are all different voltages 480/277 3ph, 208/120 3ph, and 240/120 1ph. The portable generator has cam lock connections and came with cam lock male "plugs" on long cables with no ends on the opposite side/end. The transfer switches are all installed but no provisions for attaching to the gen.They would like to have the same receptacle/connection at each location. What's the best option for this? I've never dealt with Cam lock connections and am not familiar with generators of this size. I've done all resi gens. of 20K and under.