GerryB
Senior Member
- Location
- woodbridge, ct. USA
I have a job that might be bad and have never done a mechanics lien. It is a two bedroom addition, kitchen remodel, gut bath and make two baths. The owners moved out while the work was ongoing and needed to move back in. There were many problems, starting with the addition being put up before a permit was pulled. (I didn't know that). Anyway the town gave a temp ok(not a co) to move in before the counter tops were installed. Electrically I was done except for the vanity lights in the bathroom. The plumber had a temp sink in the kitchen. Here is my situation. I am a sub-sub contractor. There is the permit contractor I'll call him, fairly good sized roofing and remodeling contractor who pulled the building permit. They have an office, a secretary, a couple of salesmen, and two project managers. Then there is the contractor who did the work. I have a contract with him and am owed $1300.00. I also have an $800.00 additional work order with the permit contractor that is not signed but was verbally agreed to by the project manager and the permit company owner on a prior walk through. About two weeks after the temp CO the counter tops went in and I finished my work. They have not gotten the final CO, about seven weeks now. Because the owner is not happy with some things I don't think they are in a hurry or letting the final inspection take place. The main permit contractor has assured me I will get paid from them for everything and they will not give their subcontractor what he is expecting. As you can see it's a mess. Anyway the permit contractor has not returned my many calls for two weeks now. The contractor I have my contract with says they owe him still and he will pay me. I am not too optimistic here, but I would at least like to file whatever I can file and not miss any deadline. I am reading three months from when you finish the job, but is the job done without a CO? Any info or advice would be greatly appreciated. Thanks.