When doing a typical service, say a 200A upgrade, and upgrading all the grounding, let's say that you have a water pipe and a pair of ground rods.
You decide to use a separate ground bar in this main panel for whatever reason, the neutral bar will have the bonding screw installed, of course.
Where do you land the #4 from the water pipe and the #6 from the ground rods? The neutral bar or the ground bar? In the end, it would be basically the same thing. But I am wondering where the code stands on this.