What's the labor unit for 2/0 SER?
George Stolz Moderator Staff member Location Windsor, CO NEC: 2017 Occupation Service Manager Feb 4, 2014 #1 What's the labor unit for 2/0 SER?
ceb58 Senior Member Location Raeford, NC Feb 19, 2014 #2 My program has it at 22 man hrs for 2 elect. per 1000 ft.
T treyp3 Member Location Fernandina Beach Fl Feb 21, 2014 #3 ceb58 said: My program has it at 22 man hrs for 2 elect. per 1000 ft. Click to expand... where did you get the program?
ceb58 said: My program has it at 22 man hrs for 2 elect. per 1000 ft. Click to expand... where did you get the program?
ceb58 Senior Member Location Raeford, NC Feb 23, 2014 #4 treyp3 said: where did you get the program? Click to expand... Craftsman Books www.craftsmanbooks.com
treyp3 said: where did you get the program? Click to expand... Craftsman Books www.craftsmanbooks.com
Little Bill Moderator Staff member Location Tennessee NEC:2017 Occupation Semi-Retired Electrician Feb 23, 2014 #5 George Stolz said: What's the labor unit for 2/0 SER? Click to expand... I realize this is a late reply, but I just saw it. So in case you still need it, here's what I have from Electrical Unit & Assembly Cost Data. unit = LF Man Hours = .085 Mat'l = 8.48 Labor = 3.32 Total = 11.79
George Stolz said: What's the labor unit for 2/0 SER? Click to expand... I realize this is a late reply, but I just saw it. So in case you still need it, here's what I have from Electrical Unit & Assembly Cost Data. unit = LF Man Hours = .085 Mat'l = 8.48 Labor = 3.32 Total = 11.79