JimmyCornholio
Member
- Location
- Virginia
Hello,
I am reviewing a plan for 240VAC double pole 40A circuit, backed-up by two individual 120VAC On-line UPS's (one for each leg). Both of the UPS outputs tie back into a double pole 40A on the load side. My concern is if either of the UPS were to fail before the other, only 1 of 2 legs would be energized creating what seems to be a safety code violation, but which one?
Thanks,
JC
I am reviewing a plan for 240VAC double pole 40A circuit, backed-up by two individual 120VAC On-line UPS's (one for each leg). Both of the UPS outputs tie back into a double pole 40A on the load side. My concern is if either of the UPS were to fail before the other, only 1 of 2 legs would be energized creating what seems to be a safety code violation, but which one?
Thanks,
JC