ryan7097
Jolt Electric LLC Owner/Operator
- Location
- Asbury Park New Jersey
- Occupation
- Electrician
I have an existing 480v 3 phase 50a breaker traveling approx 325 ft to a unistrut grid where 3 existing forklift Battery charging stations with 10a fused 3 ph 480v disconnects are located. they are in a trough tapped feeding each disconnect then to isolated 20a/480v twist lock outlets. My question is if each of the 3 chargers is a 36v dc setup can I simply add three more and tap them in the trough or do I need to run a separate 3 ph 480v 50a circuit and tap those out and copy what has been done already. My main purpose is to add 3 more charging stations for a total of 6. Any info would be greatly appreciated. Furthermore, should I install a ventilation system as well, and if so what kind? Again thanks for your thoughts.