blueheels2
Senior Member
- Location
- Raleigh, NC
- Occupation
- Electrical contractor
Im bidding a job and I have someone who is going to bring out their  trencher and trench 250'.  He'll give me a price for that but he doesn't backfill.  Anyone have a labor rate I can use to figure how long its going to take to backfill 250' of 18" deep trench.  Best guess is 5 hours but I honestly have no idea.  Residential if it matters.  Trench is from house to boat dock.
Thanks
	
		
			
		
		
	
				
			Thanks
 
				
 
 
		 
 
		 
 
		 
 
		 
 
		 
 
		