Working on a construction estimate for a client.
Deliveries are:
MCC's - 8-12 months
Panelboards - 6-8 weeks
dry type transformers - 16-23 weeks
Between the horrible increase in cost of equipment and these lead times, I really don't see this project getting off the ground!
Sure glad retirement is in my face!
Deliveries are:
MCC's - 8-12 months
Panelboards - 6-8 weeks
dry type transformers - 16-23 weeks
Between the horrible increase in cost of equipment and these lead times, I really don't see this project getting off the ground!