I have a 300' pull of 4/0 4/0 2/0 URD with a #4Al ground coming up.
I have always pulled this assembly in 2" PVC without much problem. But with the length of the run and a couple sweeps i am wondering if I should upsize to 2.5"? Will it ensure an easier pull or just be throwing money down the toilet? The cost of 2.5" is 1.5X the cost of 2" so pretty substantial.
thanks for the input