How many of you guys utlize cost codes? I heard more is NOT always better as field will not buy in.
What do you think about these?
Not sure how you you could separate overhead rough fromin wall rough. Doesn't one bleed into the others sometimes? Say a receptacle circuit may be both in wall and overhead.
Mobilization/Demobilization
Demo
Temp Power
Underground Rough
In-Wall Rough
Overhead Rough
Branch Circuit Wire Rough
Feeders
Switchgear/Panels/Transformers
Lighting
Device Trim Out
Equipment Connections
What do you think about these?
Not sure how you you could separate overhead rough fromin wall rough. Doesn't one bleed into the others sometimes? Say a receptacle circuit may be both in wall and overhead.
Mobilization/Demobilization
Demo
Temp Power
Underground Rough
In-Wall Rough
Overhead Rough
Branch Circuit Wire Rough
Feeders
Switchgear/Panels/Transformers
Lighting
Device Trim Out
Equipment Connections